The following table lists the jobs of a network along with their time estimates.
Activity T0 (Days) TM (Days) TP (Days)
1 - 2 1 3 5
1 - 3 2 5 6
2 – 4 4 6 7
2 - 5 8 10 12
3 - 5 0 0 0
3 - 6 4 8 9
4 - 7 5 7 14
5 - 7 7 10 16
6 - 7 0 0 0
6 - 8 6 9 12
7 - 9 1 3 7
8 - 9 3 5 7
i) Draw the project network
ii) Calculate the length and variance of the critical path.
iii) What is approximate probability that the job as per critical path will be completed in 24 days?
Uploaded with ImageShack.us
Tuesday, June 21, 2011
What is approximate probability that the job as per critical path will be completed in 24 days?
Posted by
Unknown
at
3:09 AM
Tags :
Critical Path
project network
Subscribe to:
Post Comments (Atom)
Search This Blog
Popular Posts
-
“You don’t inspect quality into a product: You have to build it in.” Discuss the implications of this statement. Answer. The saying, "...
-
A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two, alternatives, A and B have been identi...
-
Describe five major types of materials handling methods and name some advantages of each. Five Major Types Of Materials Handling Methods: Mo...
-
How can the relationships of different departments be considered in preparing a layout? Prepare a REL chart for the different departments of...
-
Explain different types of maintenance giving suitable example. Suggest an organisation structure for the maintenance department of a medium...
-
What are the factors considered to decide the effective capacity of a plant? Give some examples. Answer. Capacity planning is the process o...
-
What is work design? What are its constituents? Explain using a schematic diagram. What is job design? What are the behavioral aspects in jo...
-
Northwest product company uses forklift trucks to transport lumber from the mill to a storage warehouse 0.5 km away. The lift trucks can mov...
-
What do you understand by Automated Storage and Retrieval? For what kinds of goods and in which companies in India do you think such system...
-
A worker in a manufacturing industry is expected to work for a minimum of 400 minutes, in an 8-hour shift. The remaining 80 minutes is meant...